Close Window
271 - A Case Study: Optimizing the Building Envelope with a BIM-Based Framework

Speaker(s):
• Bill Coltzer Jr., AIA | President | Zero/Six Consulting
Date: 11/11/2017 | Time: 1:00 PM - 2:30 PM
Room: 4B
LUHs: 1.5 | HSW: Yes | ADA: No | GBCI: No | SD: No
Capacity: Unlimited
Through October 02: $0.00
Through November 03: $0.00
Onsite November 03: $0.00

Description
In 2015, Zero/Six collaborated with nine exterior envelope trades to create a composite envelope BIM model in order to facilitate the construction of a 432,671-sf facility. The project consisted of numerous architectural drawings, shop drawings, RFIs, and structural drawings, which multiplied the potential for schedule setbacks to arise during construction. By combining each subcontractor’s scope of work into a coordinated model, the construction team was able identify conflicts in the pre-construction phase, saving time and money during the building enclosure installation